NASHVILLE, Tenn. (WSMV) – Nissan Stadium shared updates on the construction of the new stadium.
They have begun installing the ETFE cable-stayed roof. They have installed the four of the 50 needed to complete the circular frame of the roof.
Glass railings are also being installed near the escalators along with glass handrail bases on Level 200.
New Stadium construction update as of May 29, 2025 in Nashville, TN. Photo By Donald Page/Tennessee Titans(Donald Page | Donald Page/Tennessee Titans)
Here are instructions on how to watch WSMV4 live on various platforms.
Nissan Stadium also said there is progress on the mechanical, electrical and plumbing aspects of the project.
“The first air handlers for the HVAC system are now in place at Field Level, and we’ve installed four electrical transformers that will power the substations. Plus, the permanent power connections are now live thanks to completed underground duct banks, giving the stadium not just one, but two separate power feeds for extra reliability. We also completed the domestic water connections —checking off more essentials for future operations,” said Nissan Stadium.
So far, over 220,000 square feet of concrete block walls already installed on the interior of the stadium.
Structural steel work also continues at the stadium, with a third of that part of the project complete.
“Meanwhile, offsite work is moving right along. The glazing for the exterior windows is being fabricated and is on track for installation starting this August,” said Nissan Stadium.